[Front cover:]
Camden Town station redevelopment
Environmental Statement
Non Technical Summary
London Underground Limited
Picture of
proposed office building and flats in situ.
(The picture has a logo for Environ, the company that produced the
report, inserted at the bottom.)
[Contents page:]
CONTENTS
1.0 INTRODUCTION 1
1.1 Introduction 1
1.2 Background 1
1.3 Consideration
of alternatives 3
2.0 THE PROPOSED SCHEME 4
2.1 The
new station 4
2.2 The
over station development 4
2.3 Interchange 5
3.0 SUMMARY OF ENVIRONMENTAL
IMPACTS 7
3.1 Land
use planning and built heritage 7
3.2 Visual
and townscape effects 7
3.3 Archaeology 8
3.4 Noise
and vibration 9
3.5 Air
quality 10
3.6 Traffic
and Transport 11
3.7 Water
resources 12
3.8 Land
contamination 13
3.9 Ecology 14
3.10
Microclimate 14
3.11 Socio-economic
and community effects 15
3.12
Construction phase environmental management 16
4.0 CONCLUSION 18
[Page 1:]
1.0 INTRODUCTION
1.1 Introduction
This
document is the Draft Non-Technical Summary of the Environmental Statement
for the proposed redevelopment of Camden Town station. It sets out the key
points of the Environmental Impact Assessment in
non-technical language. The Environmental Impact Assessment was
carried out by ENVIRON UK Ltd on behalf of London Underground
Limited.
Applications
for planning permission and Conservation Area Consent are being
re-submitted to Camden Council, and an application for construction powers
under the Transport and Works Act 1992 in relation to the new station, is
scheduled to be submitted in early 2003. The Environmental
Impact Assessment has therefore been undertaken in accordance with both
the Transport and Works (Applications and Objections Procedure) (England
and Wales) Rules 2000 and the Town and Country Planning (Environmental
Impact Assessment) (England and Wales) Regulations 1999.
The
objectives of the Environmental Impact Assessment are:
·
To
identify the potential environmental impacts of the proposed redevelopment
scheme, including its construction and operation, taking account of its
characteristics and any local environmental sensitivities.
·
To
predict the extent and significance of the potential
environmental impacts, and identify means for their mitigation.
·
To
assess the extent and significance of the residual impacts.
1.2 Background
[Page 2:]
Camden
Town Underground station suffers from severe congestion and poor access.
Since 1996, London Underground has evaluated more than sixteen schemes to
upgrade and modernise the station. The key problems at Camden Town station
are the small size of the ticket hall, narrow and confusing platform
access and interchange passages, inadequate platform capacity,
insufficient escalators and no step-free access.
The lack
of capacity and poor condition of Camden Town station means
that overhauling the existing building would not resolve these problems.
London Underground is therefore proposing to construct a spacious new
station for Camden Town, which would be attractive, efficient, safe and
fully accessible. Any scheme for improving Camden Town station must allow
for train and station services to be maintained during construction of the
new station. London Underground would achieve this through the
construction of a temporary ticket hall and escalator shaft at the corner
of Camden High Street and Buck Street.
In order
to construct the temporary and permanent new station, London Underground
would need to use the whole of the triangular site bounded by Camden High
Street, Kentish Town Road and Buck Street. Unfortunately, this means that
all existing buildings on the site would have to be demolished. As this
site lies within the Camden Town Conservation Area any application
for Conservation Area Consent must include proposals for replacing
the buildings cleared from the site. For this reason, London Underground
is proposing to construct a mixed-use development above the new
station. The financial return from the development would also help to
offset a proportion of the cost of the new station.
In
December 2000, London Underground submitted applications for planning and
Conservation Area Consent to the London Borough of Camden for
the redevelopment of Camden Town station, and carried out a full
public consultation exercise on its proposals. During consultation,
concerns arose, most notably about the scale and impact of the over
station development. The Mayor acting in his strategic planning role, made
it clear that he would direct Camden Council to refuse planning consent.
This scheme was
[Page 3:]
therefore
not progressed, and in consultation with Camden Council, the Greater
London Authority and Transport for London, London Underground undertook a
thorough review of the scheme.
A revised
scheme emerged from this review, which has incorporated significant
changes to the scale and design of the development, together with
improvements to the station and interchange between different modes of
public transport.
1.3 Consideration of
alternatives
It is
accepted good practice in relation to environmental assessment that some
consideration be given to alternative forms of development
and/or alternative sites for the development proposed. In this case,
however, no alternative locations for the station development are feasible
because of the fixed location of the Northem line tunnels and platforms
beneath the site.
London
Underground did, however, examine various schemes for upgrading the
station which would not have necessitated the compulsory purchase of all
property on the site, not already owned by London Underground. However, it
became clear that none of these options would provide sufficient customer
benefits over the long term. This is because demand for Underground
services is constantly increasing. By 2011, the Northern line's signalling
and control systems will have been upgraded to run 25 trains an hour on
each of the Northern line branches which meet at Camden Town, reducing
customer journey times by some 18%. Increased train frequencies mean that
stations such as Camden Town urgently need to be modernised to deal with
the expected increase in customer demand.
Since the
rejection of the previous design for the overstation development, as part
of its scheme review, London Underground has also considered a number of
alternative designs for the above ground elements in consultation with the
London Borough of Camden and the GLA. The current design
[Page 4:]
represents
the preferred option for both the ticket hall and the
commercial development.
2.0 THE PROPOSED SCHEME
2.1 The new station
London
Underground is proposing to enlarge and modernise Camden Town station,
through the construction of what is essentially a new station, linked
to the existing Northern line tunnels and platforms. The new station would
retain a ground-level ticket hall at the apex of the site, with an entrance
on Camden High Street close to its junction with Kentish Town Road. To
help ease crowding, particularly at weekends, a second station entrance at
the northern end of the ticket hall is being proposed. This entrance would
lead onto a new pedestrianised street (provisionally called 'Reunion Street'),
which would split the site north-south and provide additional circulation
space for pedestrians.
The new
ticket hall would have ticketing facilities alongside Kentish Town Road, a
fully accessible public toilet and a travel information office.
Four escalators (generally two up, two down) would link the ticket hall
with the northbound platform concourse, via a large, elliptical atrium. Short
stairs (and possibly escalators) would lead down to the southbound
concourse and platforms. There would be step-free access via a 16 person
lift between the ticket hall and platform levels and all platforms would
be made fully accessible. The station would also have three means of
emergency access and evacuation and new staff accommodation.
2.2 The over station
development
To create
a more positive impact on the surrounding townscape, the development over
the new station has been completely re-designed, and divided into two
separate sections by the new pedestrian street. At the apex of the site,
directly above the station ticket hall, there would be a five storey
[Page 5:]
office
building. The northern section of the development would include
retail space at ground level fronting Camden High Street, part of Kentish
Town Road and Reunion Street. There would also be space in the
basement (formerly occupied by the temporary station), which could be used
for additional retail or leisure purposes. Above the retail there would be
four blocks of flats grouped around an open landscaped courtyard. These
would be four and five storeys high and contain a total of seventy-two
(1-3 bedroom) flats, 50% of which would be reserved for affordable
housing. No car parking would be provided within the development, although
there would be some disabled parking spaces on Buck Street.
It is also
proposed that a new Trinity United Reformed Church should be constructed
and occupied, before the existing building is demolished. This independent
building would be positioned between two residential blocks in the centre
of Buck Street, and would enable the church to remain on site throughout
the construction period. The The final design and layout of
the church building would be decided in consultation with representatives
of the Trinity United Reformed Church.
The
over-site development has been designed to be compatible with the general
character of the Camden Town Conservation Area, whilst also providing a
'landmark' building to strengthen the urban quality of the area.
The retail
and residential development would be serviced from a managed vehicle bay
on the corner of Kentish Town Road and Buck Street. However, because of
the splitting of the site, it is not possible for this bay to
service the station and offices. Instead, the apex building would be
serviced from a vehicle bay on Camden High Street, located close to the
office entrance and the station's service core.
2.3 Interchange
As part of
the scheme review, Transport for London looked at ways of improving
interchange between different forms of public transport and
[Page 6:]
pedestrians,
and a number of their recommendations have been included in the station
redevelopment scheme.
The
proposed Cross River Tram could have its terminus on Camden High Street
adjacent to the station. The new station and tram, as well as buses and
taxis would increase Camden Town's importance as a major public transport
interchange.
[Page 7:]
3.0 SUMMARY OF ENVIRONMENTAL
IMPACTS
3.1 Land use planning and
built heritage
The scheme
proposals would include the comprehensive redevelopment of the site for a
mix of uses reflecting its town centre location. High
public transport accessibility, coupled with the need to secure
reconstruction of the station, has driven the scale and massing of the
over-station development. This is in accord with current policy of locating
high density developments close to good public transport links. However,
the scale of the development has to be balanced against the site's
Conservation Area status. The redevelopment scheme would result in
significant regeneration, not only for the site, but for Camden Town as a
whole.
3.2 Visual and townscape
effects
The
character of the area is diverse, comprising mainly
mid-Victorian townhouses and post-war infill, with some individually
notable buildings along, and at the intersection of, the main
streets.
Building
heights are mainly 3-5 storeys, but vary considerably, with some 10storey plus
buildings appearing in the background of local views. The
tallest building in the immediate area is the 8 (plus) storey Arlington
House, which can be glimpsed above the roofline on the western side of
Camden High Street. Most ground-level views are focused along the streets,
with the southern apex of the site occupying a position of relatively high
visibility at the main intersection. Longer-distance views are gained from
taller buildings and from elevated locations such as Primrose Hill and
Parliament Hill.
The
existing buildings on the site are of varied character and neither read
as a coherent group nor do justice to the potential of the site to be of
visual importance. Whilst Camden Council takes the view that some are of
minor local interest (notably the station facades, certain properties on
Kentish Town
[Page 8:]
Road, the
HSBC bank and the Trinity United
Reformed Church), others detract from the quality of nearby streets.
The
demolition of these buildings would not represent a significant loss
of buildings of architectural or historical interest. Removal of the ugly
traction sub-station on Camden High Street and of the "gap" site
occupied by Camden Market would represent a benefit in terms of the
townscape.
The new
ticket hall and office building would introduce a contemporary design into
an area in which recent development has been limited and/or relativity
understated. The glass-wrapped apex building and station ticket hall would
act as a focal point for the views along the main streets, especially from
the southern section of Camden High Street. However, the brick and render
construction of the smaller scale retail and residential element on
the north of the site, would be more respectful of the surrounding
buildings. The new pedestrian street would introduce public open space and
ensure that the development does not form a monolithic structure across
the whole site. It is expected that this street would become a lively
urban space, with shops and the station entrance making it a focal point
for people to meet. The eclectic nature of the townscape would be able to
accommodate this change brought about by the station redevelopment without
detriment. The self-assured design of the new buildings may also be
regarded as a benefit on this visually important site.
The
development would lie outside the "wider setting consultation area"
for strategic views towards the Palace of Westminster and St. Paul's
Cathedral and would not obstruct these views. Whilst just visible from
Parliament Hill and Primrose Hill, the development will be a minor new
element in these townscape views.
3.3 Archaeology
The site
forms part of an Archaeological Priority Area that encompasses Britannia
junction where Camden High Street, Parkway, Kentish Town Road,
[Page 9:]
Camden
Road and Greenland Road converge. The archaeological desk-based study produced
by the museum of London suggests that there is the potential for archaeological
resources to be present on the site. However, the presence of any
archaeological remains on the site will have been adversely affected by past
construction activities and the current structure and nature of the buildings
present on the site, in particular the Underground station and deep level Tube
shelters. As a result, some areas of the site are considered to have greater
archaeological potential than others. These latter areas include current open
ground (albeit hard-surfaced), the small yard areas within the triangle and the
line of the former Dewsbury Terrace.
Whilst
there is considered to be the potential for archaeological remains to be
present on the site, the likelihood of finding these remains intact is low or
nil for the majority of the site area due to previous construction works.
Nevertheless, deeply cut archaeological features such as wells, ditches or
quarry pits may survive in the undisturbed areas.
Therefore,
it is recommended that a Watching Brief be implemented prior to and during the
redevelopment of the site in order to determine the actual degree of
archaeological survival present.
3.4 Noise and vibration
Noise can
be defined as unwanted or undesirable sound, which can interfere with normal
activities. Related to noise is vibration which is transmitted through the
medium of ground or buildings, and can cause discomfort.
The
existing noise climate at the site is influenced by traffic. A noise survey has
been carried out as part of the environmental assessment and has demonstrated
that the site is subject to high levels of background noise. The proposed
development, upon completion, will not be inherently noisy, especially since it
would not generate additional car traffic. In addition, where possible, air
conditioning and other plant will be located internally and at roof height.
[Page 10:]
However,
construction of the new station will involve considerable excavation and use of
piling. In relation to general daytime construction works, predicted noise
levels could exceed target levels. This is largely due to the fact that
background daytime noise levels around the development already frequently
exceed the target levels. Therefore, consideration will need to be given to the
use of the quietest construction methods and the use of noise reduction
techniques. Works should also be scheduled to minimise disruption to sensitive
receptors such as the Hawley Infant and Nursery School and the Trinity United
Reformed Church.
Best
practicable means of noise and vibration control will be adopted in agreement
with the London Borough of Camden’s Environmental Health Department. General
measures currently to be adopted include use of a 3.7 m high acoustic hoarding
around the entire perimeter of the site to screen noise, and the use of ‘silenced’
plant and equipment.
Vehicle
engines will be switched off if they are standing for a significant period of
time and acoustic enclosures will be fitted to suppress noisy equipment. In
addition, methods for the construction of piles for foundations will be
selected for their low noise and vibration emission characteristics. Quieter
bored piling will be used in preference to noisy hammer-driven piling methods.
3.5 Air quality
A review
of the air quality data collected by the London Borough of Camden for Camden
Town indicates that air quality is largely acceptable in the context of the Air
Quality (England) Regulations 2000. However, in 1998 the levels of two
pollutants - nitrogen dioxide and parties (Pm10) - exceeded the objectives and
targets for air quality to be achieved by 2003. These are common air quality
problems throughout heavily trafficked urban areas. Reduction in the
concentrations of both these pollutants is anticipated due to legislated
improvements in vehicle and fuel technology.
[Page 11:]
During the
construction phase there is the potential for dust emissions from the site to
result in nuisance soiling. At particular risk are properties adjacent to the
site. Dust emissions from construction sites can be effectively controlled by the
employment of stringent management practices e.g. the use of water sprays,
screens and maximising separation distances. These will be implemented by
London Underground’s contractors adhering to the Code of Construction Practice
which will be agreed with the London Borough of Camden.
Predicted
pollution concentrations arising from emissions as a result of the completed
development show that impact on air quality should be expected to be
negligible.
3.6 Traffic and Transport
The
proposed enlargement and modernisation of Camden Town station would lead to
significant improvements in the service it provides to customers. This
improvement to public transport is in full accordance with national,
London-wide and local transport planning policies.
The
location of Camden Town station close to bus stops on Camden High Street,
Kentish Town Road and Camden Road already makes it an important interchange.
Transport for London has recommended that bus stop lay-bys should be replaced
with extended bus stop cages to allow buses easier entry into traffic flows.
The pavement on Kentish Town Road adjacent to the station would be widened and
bus stop shelters provided. The new pedestrian street and station entrance
would make interchange easier and more convenient between different bus routes
as well as between bus and Underground. It is also being proposed that,
adjacent to the station, there would be a taxi rank and cycle racks, as well as
disabled and motorcycle parking facilities on Buck Street. A new pedestrian crossing
is proposed for Camden High Street, close to its junction with Inverness
Street.
[Page 12:]
During
construction of the permanent new station, the temporary station would provide
an interim improvement over the existing station, as it would have a larger
ticket hall and a fixed staircase between two escalators.
During
construction on the site, it is likely that bus stops on Kentish Town Road
would have to be moved a few yards, but impacts on accessibility to buses would
be negligible.
By being
located at a major, and significantly enhanced, transport interchange the
over-station development would meet the aims of the Mayor’s Spatial Development
Strategy. The expected occupants and users of the development would be expected
to use public transport as no car parking would be provided on site.
The impact
and appropriate routing of construction traffic on the road network has been
considered. The maximum traffic of 40-45 lorries per day generated during peak
movement periods is expected to constitute less than 0.07% of the existing base
traffic flows on Kentish Town Road, and will not adversely affect traffic to a
significant degree. The spoil from
the site would be transported by lorry to a railhead at King’s Cross for
subsequent transport to landfill sites. However if the railhead at Kings Cross
is no longer available at the time the scheme is implemented, soil removal will
need to be undertaken by road to an approved landfill site. There would be some
37 unusual loads delivered during the construction period, and he arrangements
for these deliveries will be agreed with the London Borough of Camden and
Transport for London. The completed over-station development would not generate
car-based commuter trips, but there would be a small number of trips generated
by service vehicles.
3.7 Water resources
The
development site is not considered to be located within a sensitive area with
respect to either groundwater or surface water resources.
[Page 13:]
Although
groundwater is abstracted from the chalk aquifer in the vicinity of the site,
these abstractions are not used for public water supply. Therefore, the risk
posed by the development to groundwater resources in the area will be
insignificant.
The
nearest surface watercourse to the site, the Regent’s Canal is located
approximately 150m to the north. Owing to the distance from the site, the risk
to surface water resources from the development would be insignificant. In any
event, appropriate measures to control potential discharges of run-off from the
construction works would be implemented through the Code of Construction
Practice.
3.8 Land contamination
Only minor
potential for localised areas of ground contamination has been identified in
connection with the historic and current uses of the site, which are for
residential and commercial uses, and the Underground station.
Given that
the spoil excavated from the site is unlikely to be significantly contaminated,
the risk to site workers and other site users is considered to be low. A
procedure for the safe disposal of spoil will be implemented as part of the
Code of Construction Practice and all spoil would be disposed of at
appropriately licensed sites.
Surrounding
resources that could be affected by the development are largely limited to the
aquifer and Grand Union Canal. Due to the presence of impermeable London Clay
beneath the site and the surrounding area, such resources are not likely to be
affected. The health risk to resident and users of roads and community
facilities, including the shopping area around the site, would not be
significant, but will be addressed in a Health and Safety Plan.
Small
ground movements are anticipated during construction and completion of the
station redevelopment, and are expected to continue for a few years. A detailed
soil settlement assessment is currently in preparation
[Page 14:]
to
determine the effect of ground movement on adjoining properties. Mitigation
measures will be introduced to protect those properties that the assessment
suggests will suffer significant damage from the movement.
3.9 Ecology
The
assessment of ecological resources carried out did not identify any areas of
ecological interest or sensitivity on-site. Only one site of local Nature
Conservation interest, the Regent’s Canal, has been identified in the
surrounding area. Given that the works associated with the project will be
limited to the site itself, and the distance of the canal from the site, the
impacts of the development on the canal are not considered to be significant.
3.10 Microclimate
A
simplified desk-assessment of potential pedestrian level wind effects has been
carried out.
Overall,
it is considered that none of the proposed elements of the development would
lead to increased wind speeds for pedestrians at ground level and there are no
significant implications for surrounding buildings. As a result, no mitigation
measures are proposed.
In
relation to daylight, it is expected that the over-station development will
result in some loss to certain adjacent properties. However, in nearly all
cases the residual amount of light available would remain generally acceptable
given the urban character of the area.
Although
there will be some loss of sunlight to a variety of properties, the overall
residual sunlight following development of the over-station proposals will
remain good for a city centre site.
[Page 15:]
3.11 Socio-economic and community
effects
The
proposals for the station and over-station development aim to be regenerative.
The socio-economic impacts that are expected to result from the proposed scheme
are likely to be predominantly positive, and are summarised below:
·
creation
of between 50-100 temporary construction jobs over the seven year construction
period;
·
a
possible small increase in the number of London Underground station staff
employed on the site;
·
accommodation
for approximately 340 full time equivalent jobs linked to the office
development;
·
potential
of approximately 51 full time equivalent jobs linked to the retail development;
·
increased
availability of private and affordable housing with excellent public transport
links; and
·
station
and development fully accessible to all, promoting social inclusion.
The
adverse socio-economic impacts resulting from the permanent acquisition of land
and the proposed redevelopment, would be the loss or displacement of jobs
(including an estimated 150 part-time market stallworkers) and residential
flats (13 residents living on the site are listed on the February 2002
Electoral Roll). However, the completed development would be able to support a
substantially greater amount of employment and housing than can be accommodated
by the current premises at the site.
Mitigation
of negative socio-economic impacts deriving from the proposals is predominantly
connected to the mitigation of job losses due to building demolition and
landtake. Once compulsory purchase powers are obtained and implemented, London
Underground is committed to compensating
[Page 16:]
displaced
businesses and residents as required under statutory compensation legislation.
3.12 Construction phase environmental management
A Code of
Construction Practice will be agreed with the relevant authorities. The
contractor selected to carry out the construction works will be required to
provide a Working Method Statement for approval by London Underground and the
London Borough of Camden. This will demonstrate how the works programme to
deliver the new station will meet the obligations of the Code of Construction
Practice.
Where
departures are inevitable, prior identification will be required, so that
appropriate mitigation measures can be examined. The Working Method Statement
would address control of noise and dust, hours of working, control of run-off,
vehicle routing, road/footpath closures or diversions and waste disposal. A
designated member of the construction management team would act as a dedicated
point of contact for complaints from the local community.
The
Working Method Statement would also provide a necessary level of management and control of demolition and
construction practices. This includes advance notice of operations and the
duration of work that may cause disruption to access, noise or other
impacts. It is likely that temporary
road closures will be required for the installation of construction equipment
and utility diversions. The Code of Construction Practice, and the Working
Method Statement that would respond to its requirements, would ensure a high
level of control of potential construction impacts.
It is the
case that the Trinity United Reformed Church by staying on the site throughout
the construction period would inevitably be subject to disturbance from the
works. However, London Underground would
[Page 17:]
endeavour
to mitigate these impacts, which have to be balanced against the advantages for
the Church of a single move within the same site.
[Page 18:]
4.0 CONCLUSION
The
redevelopment of Camden Town station would yield substantial benefits in terms
of public transport provision and accessibility. The mixed-use development
above the station would be in line with current policy which favours high
density developments in areas well-served by public transport. There would also
be a net increase of jobs on-site and increased provision of residential space,
for both private and affordable housing.
The
assessment of the visual impact of the scheme has concluded that the
development would not affect strategic views of St Paul’s Cathedral or the
Palace of Westminster. The design of the over-station development has taken
account of existing urban fabric of the surrounding streets. However, the scale
of the taller station ticket hall and office building would represent a moderate
change in townscape terms and could have a beneficial impact on the character
of the adjoining streets.
It has
been demonstrated that the level of traffic expected to be generated during
construction and post-development will not affect the local road network.
Assessments of the impact of traffic generated by the development have
demonstrated that neither air quality nor the ambient noise levels in the
vicinity of the development will be significantly affected.
In an archaeological priority area, the site
is not archaeologically sensitive.
No
significant water resources or land contamination issues will arise in relation
to the completed development. Ecological impacts will also be insignificant.
Effects on
microclimate have been assessed. Effects on ground level winds will be, whilst
effects on daylight and sunlight will be affected by the introduction of the
proposed buildings on site.
[Page 19:]
As a
requirement prior to the start of the demolition and excavation works, a Code
of Construction Practice is to be developed by London Underground in
consultation with the London Borough of Camden. This would cover noise and dust
control, protection of archaeological features, control of drainage and other
relevant issues. Adherence to the Code of Construction Practice would ensure
that demolition and construction impacts are controlled to the minimum levels
feasible, and kept within acceptable limits.
The Camden
Town station redevelopment scheme would provide a solution to problems of
access and congestion in relation to the existing station. The over-station
development has been designed to create an important urban landmark in the
centre of Camden Town, which would provide additional commercial, residential,
and employment facilities in the local area. In effect, the regeneration of
this site would result in efficient use of the site with a high-density
development reflecting current government policy aspirations.
All pages marked:
Top: London
Underground Limited Non Technical
Summary of the ES - Camden Town station redevelopment
Bottom: November 2002 ENVIRON
[Keep It
Camden is concerned that this report plays down anything unpalatable, given
that Environ have dismissed Trinity United Reform Church as being of minor
importance. As such, we are inclined to
dismiss this report as a piece of paid-for propaganda and afford it little
credibility. Or in plain English - this
report is full of doodies.]